How to compute SPI and CPI from pay application data, with a $12 million example
SPI and CPI compare earned value from the pay application to the baseline plan and to job cost. This example works both for a 12-month job at month six.
Tag
Data
Logging total float on the two most critical paths at each schedule update shows how fast a job uses its cushion. This example tracks eight updates.
4 8 · -42.9% on the period
The longest path has used 26 of its 30 days of float in eight updates
Total float in work days at each monthly schedule update, example office building
Feature Data
SPI and CPI compare earned value from the pay application to the baseline plan and to job cost. This example works both for a 12-month job at month six.
| Date | Trend | Category | Title | Summary |
|---|---|---|---|---|
| Data | How to track total float across monthly schedule updates, with a 30-day example | Logging total float on the two most critical paths at each schedule update shows how fast a job uses its cushion. This example tracks eight updates. | ||
| Data | How to compute SPI and CPI from pay application data, with a $12 million example Feature | SPI and CPI compare earned value from the pay application to the baseline plan and to job cost. This example works both for a 12-month job at month six. |