How to set monthly weather delay days from NOAA climate normals, with a Chicago O'Hare example

NOAA climate normals count rain days by month at more than 15,000 stations. This example turns Chicago O'Hare's counts into a work-day weather allowance.

4.8 Dec · -9.4% on the period

May averages the most rain days at Chicago O'Hare

Average days per month with 0.10 inch or more of precipitation, 1991-2020 normals

May averages the most rain days at Chicago O'HareBar chart with 12 points from Jan to Dec. Series: Days with 0.10 in. or more precipitation. Values range from 0 to 8.0510JanMarMayJulSepDecJan: 5.2Feb: 4.7Mar: 5.5Apr: 7.1May: 8.1Jun: 6.7Jul: 5.8Aug: 6.5Sep: 5.6Oct: 6.3Nov: 5.3Dec: 4.84.8
May averages the most rain days at Chicago O'HareBar chart with 12 points from Jan to Dec. Series: Days with 0.10 in. or more precipitation. Values range from 0 to 8.0510JanJulDecJan: 5.2Feb: 4.7Mar: 5.5Apr: 7.1May: 8.1Jun: 6.7Jul: 5.8Aug: 6.5Sep: 5.6Oct: 6.3Nov: 5.3Dec: 4.84.8
Station USW00094846. Precipitation includes the liquid equivalent of snow. Source: ncei.noaa.gov
DateTrendCategoryTitleSummary
DataHow to plan winter crew hours from wind chill and the ACGIH warm-up schedule, with a steel erection exampleThe NWS wind chill formula and the ACGIH work/warm-up schedule turn a cold-day forecast into break minutes and crew hours a contractor can budget.
AINCC makes Buildots a preferred supplier after AI progress tracking lifted one project's Percent Plan Complete 2.3 timesBuildots compares 360-degree site captures with the 3D model and schedule, and NCC's Nordic building unit has signed it as a preferred supplier.
DataHow to compute unabsorbed home office overhead with the Eichleay formula, with a 60-day suspension exampleThe Eichleay formula prices home office overhead lost during a federal suspension. This example turns a 60-day suspension into a $2,000 daily rate.
DataHow to set monthly weather delay days from NOAA climate normals, with a Chicago O'Hare exampleNOAA climate normals count rain days by month at more than 15,000 stations. This example turns Chicago O'Hare's counts into a work-day weather allowance.
DataHow to price delay cost from the liquidated damages daily rate and your own field overheadFAR and FHWA rules set liquidated damages from the owner's daily costs. This example adds a contractor's field overhead and tests Saturday shifts.
DataHow to track total float across monthly schedule updates, with a 30-day exampleLogging total float on the two most critical paths at each schedule update shows how fast a job uses its cushion. This example tracks eight updates.
AITrack3D prices AI progress tracking at $0.15 per square foot and adds site photo documentation at no extra costTrack3D turns end-of-day site captures into percent complete by level, trade and area, checked against the schedule, for $0.15 per square foot.
DataHow to compute SPI and CPI from pay application data, with a $12 million example FeatureSPI and CPI compare earned value from the pay application to the baseline plan and to job cost. This example works both for a 12-month job at month six.
AIUC Irvine's CORNAV robot planner reads CAD floor plans and look-ahead schedules, raising task success from 13.0% to 72.2%CORNAV steers site robots from the 2D CAD floor plan and the weekly look-ahead schedule, and kept every planned route out of zones the schedule closed.
AIServiceTitan survey finds 62% of commercial service contractors have tried AI and 15% of users report clear ROI FeatureServiceTitan polled 1,020 commercial MEP service firms. 62% have tried AI, and ServiceTitan says 15% of AI users report clear ROI.
AISuffolk and MIT model 17% to 20% AI cost savings on one multifamily project FeatureA Suffolk and MIT white paper models 17% to 20% cost and 22% to 25% schedule savings from AI on one completed multifamily job.